Environmental Assessment Following a Diesel Spill

REDS Group were commissioned to complete environmental assessment works following an accidental diesel spill at an industrial facility.

PROJECT SCOPE

REDS Group were commissioned to complete environmental assessment works following an accidental diesel spill at an industrial facility.

Initial spill response works had cleaned up spilt fuel inside the buildings, but an unknown volume of fuel had migrated into surrounding drainage systems and areas of soft standing.

We were commissioned to carry out a full environmental assessment at the site, investigating the potential impact of underlying soils and groundwater and designing a suitable remedial strategy.

Drill Rig Site

SITE INVESTIGATION AND RISK ASSESSMENT

 

This investigation included:

Preliminary Risk Assessment


Full Intrusive Site Investigation


Detailed Quantitive Risk Assessment (DQRA)

Borehole

This investigation found: 

The initial site inspection identified the drainage system was connected to a soak-away, resulting in direct impact of underlying soils and groundwater.

The full site investigation identified hydrocarbon impact of underlying soils and groundwater that potentially posed an unacceptable risk to identified human and controlled water receptors.

A DQRA was completed to determine whether the concentrations of hydrocarbons recorded in groundwater posed an unacceptable risk

identified controlled water receptors and derive site-specific remedial targets for the site.

Drill Rig Site

REMEDIATION

 

Excavation of hydrocarbon impacted shallow soils.


Removal of impacted soils from around drainage infrastructure.


In-situ remedial treatment of the underlying groundwater using Oxygen Release Compound (ORC)

 

VERIFICATION

 

Groundwater samples were collected using low-flow sampling techniques and key groundwater parameters reviewed to confirm natural attenuation processes were active.


Dissolved hydrocarbon concentrations reduced rapidly following our remedial works, with none of the hydrocarbon concentrations recorded in groundwater found to exceed the site-specific remedial target levels for the site.

1
Response (Days on site)
5
Assessment (Days on site)
5
Remediation (Days on site)
3
Verification (Days on site)

PROJECT RESULT

We concluded the site did not pose a potential risk to identified receptors and was suitable for ongoing commercial use.

Date Posted: 10/02/2023

Categories:

Latest